Construction Progress as of May 2008 Structure
All major structural works for building and Helipad have been completed.
Elevator installation
L1 (passenger lift): installation completed
L2 (passenger lift): installation completed
S3 (service lift): installation completed
S4 (service lift): installation started
L5 (passenger lift): installation on progress
Architectural / Electrical / Sanitary Systems
- Architectural works
80% Light Weight Concrete block wall
92% Swimming pool tiling
71% Swimming pool terrace
57% Aluminium ceiling
54% Stainless and window balustrade
63% Cement plaster wall
- Electrical works
89% Bus way main feeder
- Sanitary works
65% Sewage pipe work
|