CONSTRUCTION UPDATE
Sukhumvit 31 -
Sukhumvit 39 -
Le Raffiné Jambu Dvipa Sukhumvit 39


Construction Progress as of May 2008

Structure

All major structural works for building and Helipad have been completed.

Elevator installation

L1 (passenger lift):         installation completed

L2 (passenger lift):         installation completed

S3 (service lift):             installation completed

S4 (service lift):             installation started

L5 (passenger lift):         installation on progress

Architectural / Electrical / Sanitary Systems

            - Architectural works                        

                        80% Light Weight Concrete block wall

                        92% Swimming pool tiling

                        71% Swimming pool terrace

                        57% Aluminium ceiling

                        54% Stainless and window balustrade

                        63% Cement plaster wall

            - Electrical works

                        89% Bus way main feeder

            - Sanitary works

                        65% Sewage pipe work


   
   
 
Construction Gallery  
Construction Progress as of May 2008
Unit 19B
Construction Progress as of April 2008
Construction Progress as of March 2008
Perspectives of Public Area
Unit 10B (Single type, standard)
Unit 10A (Single type, fully furnished)
Construction Progress as of February 2008
Construction Progress as of February 2007
Construction Progress as of January 2007
Construction Progress as of December 2006