Construction Progress as of April 2008

Structure

All major structural works for building and Helipad have been completed.

Elevator installation

L1 (passenger lift):   installation completed

L2 (passenger lift):   installation completed

S3 (service lift):        installation completed by June 10, 2008

S4 (service lift):        installation started

L5 (passenger lift):   installation on progress

Architectural / Electrical / Sanitary Systems

          - Architectural works                                

                                76% Light Weight Concrete block wall

                                89% Swimming pool tiling

                                62% Swimming pool terrace

                                52% Cement leveling for wooden floor

                                          44% Aluminium ceiling

                - Electrical works

                                54% MATV system

                                79% Lightning conductor

                                84% High voltage incoming

                                83% Low voltage incoming

                - Sanitary works

                                86% Ventilation system

                                62% Fire protection system

                                71% Water pipe work

                                60% Sanitary pipe work


   
   
 
Construction Gallery  
Unit 19B
Construction Progress as of April 2008
Construction Progress as of March 2008
Perspectives of Public Area
Unit 10B (Single type, standard)
Unit 10A (Single type, fully furnished)
Construction Progress as of February 2008
Construction Progress as of February 2007
Construction Progress as of January 2007
Construction Progress as of December 2006


| Top |




Copyright © 2007 "Le Raffiné, Bangkok, Thailand's Most Exclusive Development" Site Map
Site by Redlab