Construction Progress as of April 2008 Structure
All major structural works for building and Helipad have been completed.
Elevator installation
L1 (passenger lift): installation completed
L2 (passenger lift): installation completed
S3 (service lift): installation completed by June 10, 2008
S4 (service lift): installation started
L5 (passenger lift): installation on progress
Architectural / Electrical / Sanitary Systems
- Architectural works
76% Light Weight Concrete block wall
89% Swimming pool tiling
62% Swimming pool terrace
52% Cement leveling for wooden floor
44% Aluminium ceiling
- Electrical works
54% MATV system
79% Lightning conductor
84% High voltage incoming
83% Low voltage incoming
- Sanitary works
86% Ventilation system
62% Fire protection system
71% Water pipe work
60% Sanitary pipe work
|